How much does it cost to build in Dhaka in 2026? Cost per square foot, with examples

By Mahmudul Gani Kanak

November 23, 2026
10:15 PM
How much does it cost to build in Dhaka in 2026? Cost per square foot, with examples

Before you plan a house or a building of flats, it helps to know roughly what it will cost to build. In Dhaka, builders and architects talk about the cost per square foot of floor area. Here are the rates our free calculator uses for 2026, what they cover and leave out, and three worked examples.

The short answer

In Dhaka in 2026, building costs roughly Tk 3,200 to Tk 8,000 per square foot of floor area, depending mostly on the finish. Basement floors cost about Tk 5,000 to Tk 7,000 per square foot. These rates cover the structure, the finishing, the electrical and plumbing work and the site work. They leave out the land, the design fee and approvals. For example, a building of flats on a 5-katha plot, with seven floors of 2,250 square feet each, comes to about Tk 6.30 to 8.19 crore with a mid-level finish.

Cost per square foot

FinishTk per sq ft of floor area
Standard3,200 – 3,900
Mid4,000 – 5,200
Premium5,500 – 8,000
Basement floors5,000 – 7,000

Floor area means the built area of all the floors added together, the ground floor included, even when it is used for parking.

Roughly, the three finishes mean:

  • Standard: a sound building with simple finishes, such as local tiles, plaster and paint, local sanitary fittings and aluminium windows.
  • Mid: better tiles and fittings, some wood or stone, and more lights and power points.
  • Premium: imported fittings, stone or wood floors, made-to-measure joinery and more detailing.

Where the money goes

The calculator splits the cost into four parts:

PartShareWhat it covers
Structure45%foundation, columns, beams, slabs, walls and stairs
Finishing30%floors, plaster and paint, doors, windows, kitchen and bathroom finishes
Electrical and plumbing15%wiring, lights and switches, water and drainage pipes, pumps, sanitary fittings
Site work and other10%preparing the site, boundary wall and gate, drains, temporary works

What the rates leave out

  • the land;
  • the design fee for the architect and engineers;
  • approvals, such as RAJUK's permit fees (our What can I build? tool estimates them: about Tk 63,000 for the 5-katha example below);
  • furniture and appliances;
  • a lift and a generator, which a taller building usually needs.

Three examples

These come from our calculator, with the 2026 rates:

Duplex houseThree-storey houseFlats on a 5-katha plot
Floor area1,200 sq ft × 2 floors1,500 sq ft × 3 floors2,250 sq ft × 7 floors
Total2,400 sq ft4,500 sq ft15,750 sq ft
StandardTk 76.8 – 93.6 lakhTk 1.44 – 1.76 croreTk 5.04 – 6.14 crore
MidTk 96.0 lakh – 1.25 croreTk 1.80 – 2.34 croreTk 6.30 – 8.19 crore
PremiumTk 1.32 – 1.92 croreTk 2.48 – 3.60 croreTk 8.66 – 12.60 crore
  • The flats are on the 5-katha plot on a 20-foot road in Mohammadpur from our article What can you build on your plot in Dhaka?: the building may cover 62.5% of the plot, about 2,250 square feet, and rise about six floors above the ground floor.
  • One basement under it adds Tk 1.13 to 1.58 crore.
  • With the mid finish, the Tk 6.30 to 8.19 crore splits into structure Tk 2.84 to 3.69 crore, finishing Tk 1.89 to 2.46 crore, electrical and plumbing Tk 94.5 lakh to 1.23 crore, and site work and other Tk 63.0 to 81.9 lakh.

Why the range is wide

The same floor area can cost very different amounts:

  • Finish: the gap between a standard and a premium finish is the biggest single difference.
  • The ground: much of Dhaka stands on soft or filled land. A soil test shows whether the building needs piles, and how deep; deep piles add to the cost of the structure.
  • Basements: digging, holding up the sides, retaining walls and waterproofing make a square foot of basement cost more than a floor above ground.
  • Height: a taller building needs a stronger structure, and usually a lift, a generator and more fire safety equipment.
  • Prices: steel rod, cement and brick prices change through the year, and a building takes a year or more to finish.

Keeping the cost in check

  • Choose the finish level early and keep to it; changes made on site cost the most.
  • A simple structure, with columns on a regular grid and floors that repeat, costs less to build.
  • Ask contractors to price full drawings and a bill of quantities, so that their quotes can be compared item by item.
  • Keep about a tenth of the budget aside for surprises.

An architect's drawings and specifications are what make these steps possible; our article on why to hire an architect says more.

Work it out for your building

Our free construction cost calculator does these sums for your own building. Type the floor area per floor, the number of floors and any basements, choose the finish, and it shows the range and the breakdown. Not sure yet how big your building can be? Start with What can I build?: its "Estimate cost for this" link fills in the cost calculator for you.

These rates are our estimate for Dhaka in 2026; real quotes can be higher or lower. Planning to build? Talk to us.